NETWORK ANALYSIS (CPM & PERT)
            

Problem 1
A project has the following characteristics.
---------------------------------------
Activity          Duration (days)
---------------------------------------
    1-2                2
    1-4                2
    1-7                1
    2-3                4
    3-6                1
    4-5                5
    4-8                8
    5-6                4
    6-9                3
    7-8                3
    8-9                5
--------------------------------
(i) Construct a network.
(ii) Find ‘free float’ & ‘total float’ fo ...